Construction phase

Scheduling

The Project Manager must ensure that the schedule of works incorporate all the necessary Audiovisual installation activities during the construction phase, as shown in Table 3.

Table 3: Activities and Milestones in Construction Phase

Activities and MilestonesAccountableCritical Path Narrative ID
Issue notice of award to AV IntegratorBuilderMilestone
AV Shop Drawings and ApprovalAV Consultant, DST AV
Procurement of AV equipmentAV Integrator
Procurement of DTS-supplied network and computer equipmentDTS–Networks, DTS-ITAM
Install 'rough in' of AV cablingAV Integrator
Power and Data Installations in Communications RoomElectrical Contractor
Inspect and Handover the Communications RoomElectrical ContractorMilestone
Install Network SwitchesDTS–Networks
AV Equipment Install in communications roomAV Integrator
Power and data installations in class/meeting roomsElectrical Contractor
Submit UTP test results to DTSElectrical ContractorMilestone
Issue populated DNISAV Integrator
Complete IP allocations using DNISDTS–AV Projects
Complete network patching and VLAN allocations for venuesDTS–Networks
Complete Each Venue as Secure and Lockable (Clean Condition)BuilderMilestone
Test and Verify NetworkAV Integrator
Computers, iPads etc. Imaged and DeliveredDTS Desktop
AV Equipment Install in Class/Meeting roomsAV Integrator
AV CommissioningAV Integrator
Preliminary inspection of AV systemsDTS–AV Projects AV Consultant
Defects rectificationAV Integrator
Complete user acceptance testingEnd User
Final inspection of AV systemsAV Integrator DTS–AV Projects AV ConsultantMilestone
Provide technical and user trainingAV IntegratorPost PC

Note: The critical path with narrative is shown in Appendix A.

Shop drawings

The DTS–AV Project Manager must approve the shop drawings and elevations before commencement of installation activities. If any variations occur during installation, shop drawings must be resubmitted for approval.

Room handovers

The Builder must receive sign-off by DTS–Networks and the AV Integrator that communications rooms are clean, Air Conditioned, Lockable and Security Controlled before the commencement of AV, data and telephony installation. With regard to class/meeting rooms that will contain AV systems, the Builder must receive sign-off from the AV Integrator that rooms are Clean, Lockable and Security Controlled before the commencement of AV equipment installation. AV Equipment will not be accepted by DTS-AV if there is clear sign of construction dust and debris.

UTP tests and verification

The Electrical Contractor must provide DTS–Networks with the UTP test results before the commencement of any network patching and configuration activities. The AV Integrator must verify the patching and VLAN status of all network ports used by AV systems before the commencement of equipment installation.

Device and network information sheet (DNIS)

The AV Integrator must complete all the relevant fields in the Device and Network Information Sheet to enable DTS–AV to generate IP allocations and complete network port patching/configuration requests.

AV equipment will not be able to be commissioned until the DNIS is completed with the Telecommunication Outlet Number (TO), MAC Address and Device Make/Model, the Patch Request raised and actioned. This process may take up to 10 days to complete.

Equipment installation

The AV Integrator must adhere to the standards for equipment installation as detailed in AV Standards.

Commissioning

The AV Integrator must perform a final commissioning audit of the installed AV system using the supplied Auditing tool. The report on the results of the audit must be supplied to the DTS–AV Project Facilitator. For capital projects, any issues should be raised with the PCG and entered into the Issues Register.

Preliminary inspection and defect rectification

The DTS–AV team and/or AV Consultant should conduct the preliminary inspection of the class/meeting room with the AV Integrator in close attendance to quickly resolve observed defects. Other reported defects must be rectified by the AV Integrator before the User Acceptance Test (UAT). Any issues should be raised with the PCG and entered the Issues Register. Major faults will result in the abortion of the inspection, and a new inspection scheduled after the faults have been rectified.

User Acceptance Test

The nominated user group will undertake User Acceptance Testing. Faults and issues will be entered into the Issues Register and triaged to determine whether any requested changes fall within scope.

Final inspection

The AV Consultant must arrange a final inspection meeting to enable final sign-off of the room as being accepted by the University. Successful Final Inspection is required to achieve Practical Completion.

Technical and User training

The AV Integrator must provide technical training suitable for the support and maintenance to the DTS–AV team. The AV Integrator must provide basic user training to relevant University staff.

Technical and User Training may occur after Practical Completion.